How the Job Runs, Stage by Stage, on the South Coast
What happens, in what order, and where a coastal job is most likely to slip. Written in working days, because that is how a program actually behaves.
What happens, in what order, and where a coastal job is most likely to slip. Written in working days, because that is how a program actually behaves.
Licence and insurance details are provided on your discovery call, or whenever you ask. Request them →
Five minutes. Which town, house or townhouse, which room, roughly what era the place is, and what has gone wrong. That is enough to know what to bring to the measure.
About half an hour at the property. Beyond the tape measure, the things being looked at are:
Itemised, with fittings named, tile allowance stated, a repair allowance for what the walls are hiding, and a program in working days. If asbestos testing is recommended, it is on the quote as a line, not a surprise.
Tiles, tapware, vanity, screen, toilet, mirror, lighting, fan. Locked before the start date. This is the single stage most in your control and the one that most often blows a program.
Floor coverings and doorways protected, the path from the door to the skip covered. Then tiles, mortar bed, bath, shower base, vanity, toilet and wall linings come out. Noisy, dusty, and the most satisfying part to watch.
If testing has come back positive, licensed removal happens before any of this, with a clearance issued before the rest of the trades come back.
The room is bare, and this is the honest conversation. Soft joists, a termite-eaten bottom plate, a wall a long way out of plumb, pipework in worse shape than expected. Photographed, priced against the allowance, and agreed before it is fixed.
Framing repairs, noggings and solid backing where rails or a seat will go, then the plumber and electrician open up the walls: new water lines, new waste, new circuits for lights, fan and any heating. Anything moving position moves now.
Wet-area board to the walls. The floor gets a screed set to fall toward the waste, so water leaves the room instead of sitting in a corner. Falls are checked with a level, not by eye.
Membrane to the floor, up the walls in the shower, and around every junction, penetration and hob. Then it waits. Cure times are set by the product and the weather, and a humid south-coast week stretches them. This is the stage nobody should ever be talked into rushing. Detail is on the waterproofing and tiling page.
Set-out first, so the cuts land where you will not look at them and the shower niche lines up with a grout joint. Floor, then walls, then grout, then time for the grout to cure before anything gets wet.
Vanity, toilet, tapware, screen, mirror, shelves, hooks, lights, fan. Silicone last, and it needs a day before the shower is used.
Final clean, a walk-through with the list in hand, the waterproofing certificate and any warranty paperwork handed to you, and the shower run for long enough to see the water go where it should.
Wet weather. Not the trades' fault and not fixable by pushing. A humid fortnight adds days to the membrane cure, and tiling onto a membrane that is not ready is how a bathroom fails.
Laboratory turnaround. Asbestos sampling takes a few days to come back. Test early, at the measure stage, not the morning of the strip-out.
Special orders. A vanity made to a size, a screen made to a measurement, or a tile that has to come from interstate can take weeks. Order these first.
Travel. Trades servicing the area come down the highway from the north, and a half-day trade visit costs the same travel as a full day. Stages get grouped deliberately, which is why you sometimes see nobody for a day and then three people at once.
Owners corporation approval. Townhouses and units need consent where waterproofing is replaced, and committees meet on their own schedule. Start that paperwork before you set a date.
Give us the booking you cannot move. The program is written backwards from it, with contingency days built in rather than assumed away, and the quiet months between autumn and spring used where possible. More on that on the rental and holiday-let page.
Run the fan for at least fifteen minutes after every shower. Rinse salt off outside hardware. Keep an eye on the silicone at the floor junction in the first year and say something early if it lifts — a bead of silicone is a five-minute job, and the thing it protects against is not.
The cost page has the guide tiers, and the questions and answers page covers the rest.
Renovation work is carried out in partnership with Coastal Renovation Group, a licensed NSW builder. Licence and insurance details are provided on request.
Call 02 4214 4021 or send the room details through.
For most main bathrooms, somewhere between three and a half and five weeks on site. Brick veneer on a slab with nothing moving sits at the short end. An older cottage with asbestos removal, floor repairs and new pipework sits at the long end.
Late selections, by a wide margin. If the tiles, vanity or tapware are not on site when the trade is, the job stops and the trade goes to the next one. After that it is what appears behind the old linings, and wet weeks slowing the membrane cure.
That is how most short-stay jobs down here are programmed. You give us the first booking you cannot move, we work backwards from it with spare days built in, and selections are locked before the strip-out rather than during it.
Not for most of it. You need to be reachable at the start, when the room is first opened up and anything unexpected is found, and for the handover walk-through at the end.